The authority was required to produce an updated defect condition report for a 180+ kilometre provincial road network as input to the following financial year maintenance budget. Previous audits had been conducted on foot by rotating inspection teams, a process that took four to six months and returned subjective, inconsistent grading. Budget deliberations were moving faster than the audit cycle could keep up.
The authority needed three changes. Objective and repeatable defect classification. GPS-accurate defect positioning so maintenance tenders could be issued against verified locations. And full network coverage in a timeframe that fitted the budget decision window. TMH9 compliance was non-negotiable.
Off-the-shelf pavement management systems either required dedicated survey vehicles the authority did not own, or returned output that could not be aligned with TMH9 without significant manual work.